← Back to NPWR filing summaryThis is the extracted source text from the SEC filing. Formatting may differ from the original document.
As a smaller reporting company, we are not required to provide the information called for by this Item. We are nonetheless providing the risk factors set forth below, which reflect risks associated with recent developments in our business and strategy. These risk factors supplement and, to the extent inconsistent, supersede the risk factors disclosed in Part I, Item 1A of our Annual Report, which you should also carefully consider. The risk factors below are not a complete statement of the risks we face.
We may be unable to negotiate and enter into binding power offtake agreements on acceptable terms, on our anticipated timeline, or at all, which would adversely affect our ability to reach a final investment decision
37
Table of Contents
and obtain project financing for Project Permian Phase I.
We are engaged in a process intended to result in one or more power offtake agreements for Project Permian Phase I. Discussions, indications of interest, requests for proposals, term sheets, memoranda of understanding and similar instruments do not constitute binding commitments unless and until definitive agreements are executed. If we are unable to execute binding power offtake agreements at prices and on terms sufficient to support project economics and financing, our final investment decision, construction commencement, and commercial operation dates could be delayed or may not occur, and our liquidity and capital requirements would be adversely affected. We also expect that any power offtake agreement we enter into would require us to provide substantial reciprocal credit support, in the form of cash, letters of credit or guarantees, scaled to the capacity committed and maintained through development, construction and operations, which would further reduce the liquidity available to us for other purposes.
Demand for the power we intend to sell is concentrated in a limited category of large-load customers whose electricity requirements depend on capital investment cycles that may not continue at current levels.
Our offtake process for Project Permian Phase I is directed primarily at data center developers, computing infrastructure providers and other large-load customers whose electricity requirements reflect sustained capital investment in computing capacity. That investment is concentrated among a limited number of counterparties and is discretionary. A reduction, deferral or geographic reallocation of capital spending by these counterparties (whether resulting from changes in expected returns on computing investment, financing conditions, technological developments that reduce power intensity per unit of computing output, siting, permitting or community opposition constraints, regulatory or governmental restrictions on the development or interconnection of data centers, including in ERCOT, or general economic conditions) could reduce the number of potential offtakers, extend negotiation timelines, or reduce the pricing, contract tenor or capacity commitments available to us. Because we expect to rely on long-term offtake agreements to support project-level financing, the concentration, contract tenor and creditworthiness of our counterparties will also affect our ability to obtain financing on acceptable terms. We may be unable to identify alternative customers for capacity developed in reliance on this demand.
Our business strategy has changed substantially, and our project configurations may include natural gas generation deployed in advance of, or without, carbon capture.
We have repositioned our business to focus on natural gas power generation for co-located large-load customers, initially without carbon capture, and we have indefinitely suspended development of the Oxy-Combustion Cycle. We do not currently expect the initial phase of Project Permian to include carbon capture, and any later deployment of carbon capture would depend on definitive technology, customer and financing arrangements. This repositioning reflects, among other things, current market conditions in which many prospective customers prioritize the speed and quantity of reliable power over carbon abatement and may be unwilling to pay a premium for lower-carbon power in the near term. The configuration, capacity and carbon capture scope of each phase of our projects, including Project Permian Phase I, will depend on our ability to in-license any necessary post-combustion carbon capture technology, customer requirements, commercial arrangements, equipment availability and financing, and may include natural gas generation deployed in advance of, or without, carbon capture. Our ability to deploy carbon capture technology at our projects is dependent on our ability to negotiate and enter into definitive commercial arrangements to license post-combustion carbon capture technology from Entropy or another provider. If we are unable to reach such definitive agreements, we may be unable to offer carbon capture at our projects, which would materially and adversely affect our business prospects.
We may be unable to realize any value from our Oxy-Combustion Cycle intellectual property and the La Porte Demonstration Facility, which have been fully impaired.
During the second quarter of 2026, we recognized a full impairment of the Developed Technology Asset Group, and those assets are carried at no value. We have no current plans to resume development of the Oxy-
38
Table of Contents
Combustion Cycle, and any recovery of value would depend on a sale or other disposition of all or part of the Oxy-Combustion Cycle intellectual property and our improvements, equipment, and lease interests at the La Porte Demonstration Facility. We have not entered into any binding agreement for such a transaction, Baker Hughes' exclusive rights with respect to the La Porte Demonstration Facility remain in effect and may limit the terms or universe of potential counterparties, and there can be no assurance that any transaction will be agreed or consummated, or as to its terms or timing. In addition, we have revised the expected decommissioning timing for the La Porte Demonstration Facility to June 2027, and the actual timing and cost of decommissioning, or the treatment of those obligations in any disposition, may differ from our current estimates.
Our pursuit of co-located large-load projects exposes us to execution risks that are new to us and to governmental intervention in Texas, any of which may delay, restrict, or prevent our projects.
We are pursuing the development of power generation projects for co-located large-load facilities such as data centers. Activities of this type are new to us and may expose us to risks we have not previously borne including land acquisition and site-control risk, construction and counterparty risk, contractual performance risk, regulatory risk, and additional capital requirements at a time when we do not have sufficient committed capital to fund Project Permian Phase I through commercial operation. If a co-located facility requires grid-supplied power, whether as a supplement or as backup, we or our customer would be subject to large-load interconnection processes and to competition for available capacity, either of which could delay the project. We may also face competition for sites, interconnection positions, and end users from parties with substantially greater resources and relevant experience. We currently hold only a portion of the land rights required for the contemplated co-located configuration and broader build-out at Project Permian, and we have not obtained the additional land or development rights that configuration would require. If we do not obtain those rights on acceptable terms, Project Permian may be limited in size, delayed, reconfigured or not developed. To preserve schedule, we may also commit material capital to power generation equipment and related engineering before binding offtake, land, partner and project-financing arrangements are in place, and if a project does not proceed, a portion of those expenditures may not be recoverable. If these activities are unsuccessful, we could incur costs without corresponding benefit, and our results of operations, liquidity, and project timelines could be materially and adversely affected.
These processes are also subject to intervention by Texas state officials. On August 3, 2026, the Governor of Texas directed the Public Utility Commission of Texas and ERCOT to conduct a comprehensive verification and audit of all data center projects advancing through ERCOT’s interconnection process before any additional data center projects are approved to move forward, and directed that any project failing to comply with applicable requirements be denied connection to the Texas grid. The directive requires the collection of information from each data center project regarding public financial assistance received or expected, projected electricity consumption and any on-site generation, projected water consumption and cooling technology, measures to mitigate impacts on neighboring communities, and project ownership and control. The Governor has also indicated that he intends to work with the Texas legislature to address concerns regarding data centers.
We cannot predict the scope, duration, or outcome of this process, the requirements the Public Utility Commission of Texas or ERCOT may adopt in response, or any resulting legislation. The process may delay or prevent the interconnection of data centers and other large loads that we expect to serve, extend the timelines on which prospective customers are prepared to commit to power offtake, alter the criteria on which customers select sites, or reduce the number of prospective customers able to proceed in ERCOT. Any of these outcomes could delay or prevent our reaching a final investment decision for Project Permian Phase I, delay or prevent project-level financing, and adversely affect our business, financial condition, results of operations, and prospects.
Grid interconnection and related regulatory processes, including ERCOT’s recently adopted batch framework for interconnecting large loads, may delay or restrict our projects.
Our projects may require timely interconnection to the ERCOT grid and, for behind-the-meter configurations, may depend on the large-load interconnection processes applicable to co-located loads, whether those loads are
39
Table of Contents
developed, owned, or contracted for by our customers, our partners, or us. These processes are new, evolving, and subject to eligibility criteria, timelines, financial-security requirements, and allocation decisions outside of our control. Delays or adverse outcomes could delay project development, increase project costs, reduce the attractiveness of our projects to customers, and adversely affect our results.
We depend on the availability, cost and delivery timing of power generation equipment and related long-lead equipment.
Manufacturer backlogs for power generation equipment, including gas turbines, and related equipment currently extend multiple years. Although we have contracted for certain turbine equipment for Project Permian Phase I, changes in delivery schedules, cost escalation, supplier performance or the loss of reserved manufacturing slots could delay our projects and increase their cost, and replacement equipment may not be available on acceptable terms or timelines, or at all. Prevailing market prices for equipment comparable to the units we have contracted have increased materially since we contracted for them, and any additional equipment we procure is likely to cost more than the equipment we hold.
We do not have a binding agreement for the post-combustion carbon capture technology, which is an important pillar of our long-term strategy.
Our prior letter of intent with Entropy has expired by its terms and has not been replaced, and our discussions with Entropy are continuing on a non-binding basis. Either party may discontinue negotiations at any time, and any framework we agree is not expected to provide for exclusivity or an equity investment by us in Entropy. We have not agreed on the structure, scope, economics or timing of any definitive arrangement, and any definitive arrangement may require capital commitments, licensing fees or other payments in amounts and on timing that have not been determined. If we are unable to enter into definitive agreements on commercially acceptable terms, we would need to identify and qualify an alternative technology provider, which would require additional time and expense, may not be available on terms or timelines supporting our project schedules, and could prevent or delay carbon capture in later phases.
Our project economics depend in part on carbon capture tax credits, which are subject to availability, transferability, monetization and other restrictions.
The economics of projects incorporating carbon capture depend in part on federal tax credits, including the credit under Section 45Q of the Internal Revenue Code, the value, transferability and monetization of which are subject to statutory and regulatory requirements, including restrictions relating to foreign entities of concern. The credit value available with respect to any project will depend on, among other things, when the applicable facility or equipment is placed in service, whether prevailing wage and apprenticeship requirements are satisfied, and the manner in which captured CO₂ is stored, used, or otherwise disposed of, and legislation enacted in 2025 that increased certain credit values, including for CO₂ used in enhanced oil recovery, may be amended or repealed. If such credits are unavailable, reduced, restricted or cannot be efficiently monetized, our project economics and offtake pricing could be adversely affected.
Customers may not attribute value to carbon capture, and regulatory developments may reduce requirements that would otherwise support demand for lower-carbon generation.
Our long-term strategy contemplates that some customers may eventually value, and pay for, power generated with carbon capture. Our near-term strategy does not assume that customers will pay a premium for lower-carbon power, and the initial phase of Project Permian is not currently expected to include carbon capture. Recent development activity in our target markets has emphasized speed to power, available capacity and price, and certain large purchasers of electricity have modified or extended timelines associated with previously announced emissions commitments. In addition, federal greenhouse gas emission standards applicable to fossil fuel-fired electric generating units, and related greenhouse gas reporting requirements, are subject to pending regulatory action. If applicable emissions requirements are reduced or eliminated and customers do not independently attribute value to carbon capture, pricing available for lower-carbon power may not exceed
40
Table of Contents
pricing for conventional generation by an amount sufficient to recover the incremental capital and operating costs of carbon capture. In that event, we may deploy generation without carbon capture, defer carbon capture investment, or realize returns below those we currently anticipate.
We compete for customers, equipment and capital with substantially larger and better-capitalized participants, including participants pursuing gas generation with carbon capture.
Following the repositioning of our business, we compete directly with integrated energy companies, independent power producers, equipment manufacturers and developers pursuing natural gas generation for large-load customers, including projects incorporating carbon capture. Many of these participants have greater financial resources, lower costs of capital, established customer relationships, existing carbon dioxide transportation and sequestration infrastructure, priority access to constrained equipment manufacturing capacity, and the ability to commit capital in advance of securing offtake. We may be unable to compete successfully on schedule, price or credit terms.
We may be unable to obtain the capital required to develop our projects, and our share price, public float, and changed asset base may limit our access to capital, result in substantial dilution, and affect the continued listing of our securities.
Following the impairment of the Developed Technology Asset Group, our assets consist primarily of cash, cash equivalents and investments, and deposits on gas turbine equipment for Project Permian Phase I. We have no revenue, no binding power offtake agreement, and have not made a final investment decision for Project Permian Phase I, and we do not have sufficient committed capital to fund the project through commercial operation.
Our ability to raise equity capital depends on the market price of our Class A Common Stock and on the aggregate market value of our common equity held by non-affiliates. If and for so long as that value is below $75 million as of the applicable measurement dates under the instructions to Form S-3, the amount of securities we may sell in primary offerings under an effective shelf registration statement during any 12-month period is limited to a portion of that value. A decline in the market price of our Class A Common Stock would further reduce the capital available to us through such offerings, increase the dilution to existing stockholders resulting from any equity issuance, and could make equity financing unavailable on acceptable terms or at all. In addition, share-settled payments under the BHES JDA made when the ten-day volume-weighted average price of our Class A Common Stock is below $4.00 per share require incremental cash payments, as described in Note 12.
Our Class A Common Stock and warrants are listed on the New York Stock Exchange and are subject to its continued listing standards, including a requirement that the average closing price of a listed security not fall below $1.00 over a consecutive 30 trading-day period. The market price of our Class A Common Stock has been volatile. If we fail to satisfy applicable continued listing standards and do not cure the deficiency within the applicable period, our securities could be suspended from trading and delisted, which would further impair our access to capital and reduce the liquidity of our securities.
We are subject to the risk of becoming an investment company.
We are an energy technology and project development company. We are not primarily engaged in the business of investing, reinvesting or trading in securities, and we do not hold ourselves out as being engaged in those activities; our historical development, our public representations and the activities of our officers and directors support the conclusion that we are an operating company. Under the Investment Company Act of 1940, as amended (the “ICA”), however, a company may be deemed an investment company if the value of its investment securities exceeds 40% of its total assets (excluding government securities and cash items) and no exception or safe harbor applies. Pending its use in our primary business, we invest cash, including cash obtained in connection with our 2023 merger, in highly liquid available-for-sale securities, including corporate bonds, to conserve capital and liquidity, and as a result of recently recognized impairment losses those securities constitute a larger portion of our total assets than previously. To maintain compliance with the ICA, we monitor
41
Table of Contents
the value of our investments, and we may need to divest securities, make investments that are less advantageous than if we did not have ICA concerns, or forgo otherwise desirable investments or transactions.
Rule 3a-2 under the ICA provides a one-year grace period for a transient investment company that has a bona fide intent to be engaged primarily in a non-investment business, but the grace period is available no more than once every three years and may not be available when we seek to rely on it, and reliance on it could require us to dispose of securities or limit our investments, joint ventures or other activities.
We intend to conduct our business so that we are not deemed an investment company, but there can be no assurance that we will succeed. If we were deemed an investment company, we would be required to register under the ICA, obtain exemptive relief, or modify our business and organizational structure to fall outside the definition. Registration would subject us to substantial regulation concerning management, operations, transactions with affiliates and portfolio composition, which would significantly affect our ability to operate as contemplated and could have a material adverse effect on our business, financial condition and results of operations. If we failed to register when required, we could be subject to monetary penalties or injunctive relief in an action brought by the SEC, and we could be unable to enforce contracts with third parties.
We are subject to a pending securities class action and a related stockholder derivative action, and may become subject to additional litigation or regulatory proceedings, any of which could result in substantial costs and divert management’s attention.
We are a defendant in a putative federal securities class action and a related stockholder derivative action, in each case arising from alleged misstatements concerning the timing and costs of developing Project Permian. These matters are described in Part II, Item 1, “Legal Proceedings,” and in Note 14 to our condensed consolidated financial statements. We intend to defend these matters vigorously, but we cannot predict their outcome, and we are unable to estimate a reasonably possible loss or range of loss.
Litigation of this type is expensive, may continue for years, and diverts the attention of management and other personnel from our business, regardless of outcome. An unfavorable ruling or a settlement could require us to pay substantial amounts, and our insurance may be insufficient, subject to significant retentions, or unavailable for some or all of these matters. We also have indemnification and expense-advancement obligations to our current and former officers and directors. The underlying events, these actions, or our disclosures regarding them could give rise to additional litigation or to inquiries or investigations by regulatory authorities.
Additional risks and uncertainties not presently known to us, or that we currently deem immaterial, may also materially and adversely affect our business, financial condition, results of operations, and prospects.