We lease offices and own data center sites in the United States, Canada, Australia and Spain.
The following table reflects our announced data center properties as of June 30, 2026, that are either operating, undergoing retrofitting, under construction or in development, along with their actual or expected respective power capacity in gross MW and acreage held in freehold, some of which are subject to encumbrances. We have an additional multi-GW development pipeline beyond these announced data center sites.
104
Site Capacity(MW)
Canal Flats (British Columbia, Canada) 30
Prince George (British Columbia, Canada) 50
Mackenzie (British Columbia, Canada) 80
Childress (Texas, USA) 750
Sweetwater 1 (Texas, USA) 1,400
Sweetwater 2 (Texas, USA) 600
Kiowa (Oklahoma, USA) 1,600
Badajoz, Extremadura, Spain 300
Bundey (South Australia, Australia) 800